From June 16 to Aug. 24 construction work on UCA Level 5 will occur in the W526 area. Contractors will be starting construction on the UCA 5 new washrooms.
Results from July 9th to 30th, 2025 for Campus Community & Facilities
There is a geotechnical investigation starting around the perimeter of University Hall on Thursday, July 3 and will continue through to approximately Wednesday, July 30.
Please be advised that contractors will be doing some concrete coring in W526 on Wednesday July 16, 8 a.m. to noon. During this time a portion of the W4H19 corridor will be closed to public to ensure safety.
Please be advised that on Wednesday, July 23, starting at 7:30 a.m., contractors will be working in the Subway space in University Hall, Level 6 removing floor tile.
*This planned procedure has been cancelled*
Please be advised that the domestic water shutdown for University Hall and the University Centre for the Arts that was scheduled for tonight has been cancelled due to unforeseen circumstances.