living wall repairs

This notice is from the archives of The Notice Board. Information contained in this notice was accurate at the time of publication but may no longer be so.

Commencing at about 4 pm on August 2 crews will be erecting scaffolding to make repairs to the rail used for maintaining the living wall. The work will consist of cutting the defective rail off near the ceiling and then welding a new rail in its place. This process is expected to last two days but most work will take place during the evening and nightime hours. Contact Phil Dyck for questions or concerns.403-795-1314


Contact:

Phil Dyck | phil.dyck@uleth.ca | (403) 329-2608